** Is paypal not accepting your debit/credit card ? You can tranfer money from your bank account also. please email to sales@certchamp.com to get details.

Project Time Management PMP Sample Questions



200 PMP 4th Edition Questions - Free
1630 PMP 4th Edition Questions



PMP Exam Tips
PMP Exam Preparation
PMP Exam One Page Formula's


    Share   
Project Time Management

1. Define Activities


2. Sequence Activities


3. Estimates Activity Resources


4. Estimates Activity Durations


5. Develop Schedule


6. Control Schedule


These questions are randomly taken from certchamp PMP exam kit



Question - 2

An activity has an Early Finish(EF) of 5 days and Late Finish(LF) of 16 days.What is activity's float ?
1.11 days
2.21 days
3.5 days
4.16 days

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Activity float = Late Finish - Early Finish = 16-5 = 11 days



Question - 6

You are project manager of a project and you have decided to CRASH the project. Which of the following is the most likely outcome of this ?
1.increased cost
2.added risk
3.increased project time
4.doing activities in parallel

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. CRASHING is reducing project time by expending additional resources. Therefore option A is true.



Question - 33

You are the project manager for the large Project. You are identifying and documenting relationship among the project activities. This process is called ______?
1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule

Correct Answers are : 2
Explanation :
B is the correct answer.

B is the correct answer. Sequence Activities - identifying and documenting relationship among the project activities. PMBOK Page no 167.



Question - 38

You are the project manager for the large Project. You have identified and documented relationship among the project activities and created project schedule network diagram. What is your NEXT step ?
1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule

Correct Answers are : 3
Explanation :
C is the correct answer.

C is the correct answer. project schedule network diagram is input of Develop Schedule. PMBOK Page no 168.