Project Scope Management PMP Sample Questions
200 PMP 4th Edition Questions - Free
1630 PMP 4th Edition Questions
PMP Exam Tips
PMP Exam Preparation
PMP Exam One Page Formula's
Share
Project Scope Management Processes
1. Collect Requirements

2. Define Scope

3. Create WBS

4. Verify Scope

5. Control Scope

Question - 10
You are a project manager of a large project and you are identifying some alternative techniques to generate different approaches to execute and perform the work of a project. You are doing it as a part of:
1.Collect Requirements
2.Control Scope
3.Verify Scope
4.Define Scope
Correct Answers are : 4
Explanation :
D is the correct answer.
This is call an Alternative Identification in the Define Scope process.
Question - 31
You are a project manager and the project is to install ACs into hotel rooms. You did project cost and time estimates and informed the customer that the project estimates will be accurate if the requirements such as wooden coating are met. This is an example of which of the following?
1.Risk
2.Assumption
3.Constraint
4.Budget analysis
Correct Answers are : 2
Explanation :
B is the correct answer.
This is an example of assumption because estimates provided will be accurate if the rooms meet the requirements like (wooden coated). A and C are incorrect because the scenario did not describe a risk or constraint.
Question - 46
You are the project manager for a project to create a new product for the marketing industry. You recently came to know that a competitor is also working on a similar project with an additional web-based tool, which your project does not offer. You initiate a change request to update your project. This is an example of:
1.A change due to an external event
2.A change due to an error and omission in the initiation phase
3.A change due to an error or omission in the planning phase
4.A change due to a legal issue
Correct Answers are : 1
Explanation :
A is the correct answer.
The change is requested to remain competitive with the competition an external event.
Question - 47
You are a project manager of a pharmaceutical company. A new pharmaceutical regulation is passed that changes your project scope. For the project to be in accordance with the new regulation, what should be your next action?
1.Present the change to the Change Control Board (CCB)
2.Notify Management
3.Prepare a new baseline to reflect the changes
4.No need to do anything
Correct Answers are : 1
Explanation :
A is the correct answer.
You must present the change to the Change Control Board (CCB) for new changes.