Project Procurement Management PMP Sample Questions
200 PMP 4th Edition Questions - Free
1630 PMP 4th Edition Questions
PMP Exam Tips
PMP Exam Preparation
PMP Exam One Page Formula's
Share Project Procurement Management
1. Plan Procurements

2. Conduct Procurements

3. Administer Procurements

4. Close Procurements

Question - 1
At what part of the Procurement Management process does procurement negotiations happen?
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 2
Explanation :
B is the correct answer.
The negotiations happen at the Conduct Procurements of the Procurement process.
Question - 2
The RFP (Request for proposal) is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation :
A is the correct answer.
RFP(Request for proposal) is done in Plan Procurements process,
Question - 3
The Create Procurement document is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation :
A is the correct answer.
The Create Procurement document is done in the Plan Procurements process.
Question - 4
Make-or-Buy Analysis is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation :
A is the correct answer.
Make-or-Buy Analysis is done in the Plan Procurements process.
Question - 5
You are a project manager and now you are comparing proposals received from sellers. Comparing proposals received from sellers is done in _______ .
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 2
Explanation :
B is the correct answer.
Comparing proposals received from sellers done in the Conduct Procurements.