** Is paypal not accepting your debit/credit card ? You can tranfer money from your bank account also. please email to sales@certchamp.com to get details.

Project Procurement Management PMP Sample Questions



200 PMP 4th Edition Questions - Free
1630 PMP 4th Edition Questions



PMP Exam Tips
PMP Exam Preparation
PMP Exam One Page Formula's


    Share    Project Procurement Management

1. Plan Procurements


2. Conduct Procurements


3. Administer Procurements


4. Close Procurements


These questions are randomly taken from certchamp PMP exam kit
Question - 1

At what part of the Procurement Management process does procurement negotiations happen?
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements

Correct Answers are : 2
Explanation :
B is the correct answer.

The negotiations happen at the Conduct Procurements of the Procurement process.



Question - 2

The RFP (Request for proposal) is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements

Correct Answers are : 1
Explanation :
A is the correct answer.

RFP(Request for proposal) is done in Plan Procurements process,



Question - 3

The Create Procurement document is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements

Correct Answers are : 1
Explanation :
A is the correct answer.

The Create Procurement document is done in the Plan Procurements process.



Question - 4

Make-or-Buy Analysis is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements

Correct Answers are : 1
Explanation :
A is the correct answer.

Make-or-Buy Analysis is done in the Plan Procurements process.



Question - 5

You are a project manager and now you are comparing proposals received from sellers. Comparing proposals received from sellers is done in _______ .
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements

Correct Answers are : 2
Explanation :
B is the correct answer.

Comparing proposals received from sellers done in the Conduct Procurements.