Project Communications Management PMP Sample Questions
200 PMP 4th Edition Questions - Free
1630 PMP 4th Edition Questions
PMP Exam Tips
PMP Exam Preparation
PMP Exam One Page Formula's
Share
Project Communications Management
1. Identify Stakeholders

2. Plan Communications

3. Distribute Information

4. Manage Stakeholder Expectation

5. Report Performance

Question - 8
Emails and voice mails are example of ______.
1.Interactive Communications
2.Pull Communication
3.Push Communication
4.Noise
Correct Answers are : 3
Explanation :
Video Conferencing, phone calls, etc. are examples of Interactive Communication. Letter, memos, faxes , email etc are example of Push Communication. Internet site, e-learning etc are example of Pull communication. PMBOK page no 287.
Question - 59
What is the difference in the number of channels between five people and three people?
1.7
2.2
3.5
4.8
Correct Answers are : 1
Explanation :
A is the correct answer.
Number of communication channel will be calculated using formula n*(n-1)/2 where n is the number of people involved in the communication. Then Number of communication channel for 5 people is = 5(5-1)/2=5*4/2=10 , Number of communication channel for 3 people is = 3(3-1)/2=3*2/2=3, So Difference is 10-3 = 7
Question - 29
You are a project manager of a project and want to report the actual project result and the planned status. You should use?
1.Forecasting report
2.Trend reports
3.Status report
4.Variance report
Correct Answers are : 4
Explanation :
variance report: An actual project result and planned status of a project.